  1. I wish to set Active Directory account expiry to 12 hours after being generated.  I'm using the Calculate Working Date/Time utility and then formatting the date to the required output to send to AD and this is working fine, however when I check the AD account I notice that the expiry is set to the end of the previous day and there is no scope for the time to be included.  Is there an alternative way to achieve a 12 hour expiry? 

    The request could be initiated on any given day / time so should not end at midnight as in theory it could have been requested at 23:55 and still be needed for the full 12 hours, not 5 minutes!  Thanks in advance

    image.png.63435a24f9b17bd3d354a80ed8e277a6.pngimage.png.d5fcbe53c201b5f5cdc9b535b33d62d6.pngimage.png.3f6d879cbacc01e762e444b1d142d6af.png

  2. I have added a Change Freeze which the covers Christmas and New Year period and this is showing nicely in grey in the change calendar, but I may be missing some things and therefore have a couple of questions:

    • Is there a way to stop changes being scheduled during the change freeze period (during logging)?  It seems that a change cannot be rescheduled during the change freeze period once logged, which works well, but can still be logged in the first place
    • Could the Date & Time control be greyed out or show the change freeze period, in the same way it shows Bank Holidays?  Or should I be adding the Change Freezes to the Working Time Calendar as well as the Change Calendar?

    Any other suggestions on how to better manage Change Freeze periods without manual intervention?  Thanks in advance

  3. +1 

    Is there / could there be greater control over the colour scheme for Tasks and Milestones, including the thresholds at which the colours change?  As mentioned by @Damola our organisation uses Red to show that a task / milestone / project is overdue or in trouble, not that the progress has not yet reached 30% complete, we use Blue for complete, etc, etc.  Its hindering the progress of our implementation of Project Manager because the colours conflict with our existing projects.  Any advice appreciated.  Thanks

×
×