Ann Posted March 15, 2021 Posted March 15, 2021 Afternoon All Hope you are safe and well. Please would it be possible to help/advice how the RAG status works within Project Manager? We have found that the RAG Status can be changed manually but does this work automatically at all please? Also is there a way that an incomplete/overdue task or milestone can be marked in some way as Late, as opposed to In Progress please? Thank you. Kind Regards Ann
AlexTumber Posted March 15, 2021 Posted March 15, 2021 @Ann thanks for your post. The idea with a project RAG Status is to give an overall indication of how the project is going. The RAG Status can be set manually, or automatically calculated based on the project rag tolerances. The setting to control this is available to the Project Manager of each project. You can define rag tolerance matrices in the Hornbill Admin Tool. Overdue project tasks have their due date highlighted in red. I can ask our development team about the possibility of adding the same functionality to milestones. Alex
Nikolaj Posted March 15, 2021 Posted March 15, 2021 @AlexTumber you show a RAG Status for Tasks in your picture. How can i do this? I cannot find it and also no setting for it. thanks and best regards Nikolaj 1
Nikolaj Posted March 15, 2021 Posted March 15, 2021 @AlexTumber also the estimated hours in your picture? is it a new version you are showing? Thanks Nikolaj
AlexTumber Posted March 15, 2021 Posted March 15, 2021 @Nikolaj yes - a new update coming this week :-) Alex 1
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now