Hello Support @AlexTumber

I have 2 things regarding the Gantt Chart.

1. If you have 2 Milestones on the same day it will not show both in the Gantt chart only one. Here for example 18.06.2019

image.thumb.png.c367084e368c65b5d77986188b1ac013.png

image.png.342983ae79e9b4086fae4180ea7e1227.png

2. If you set a filter in the "list view" and then go to gantt chart and edit the range from ... to...

I can only see tasks who start and end in this time. But not tasks how are already in work and the finish date is in that time. It would be really nice to see also the tasks  are in progress

image.png.c33567849483751c6d88549bd3622616.png

image.thumb.png.6191edf2c87ffabc8e5e5eda629414ce.png

Thanks

Nikolaj

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...