I have a bunch of sequential tasks that show like this in the Gannt view:
image.png.795d083136815d32d14eae1165f0c18b.png

When I activate the Use Summary Tasks button the order changes and it seems the start date is ignored, have I missed something?
image.png.06aaeb633c1fb90127492225879e237f.png

Posted

@Sam P thanks for your post.

It's difficult to tell from just a screenshot but I would hazard a guess that this is a data issue. Can I ask if all of your project tasks have start and end dates?

Alex

Posted

@AlexTumber just created a new Project from template and this seems to be OK now.

I have a feeling some of the tasks in the example shown above did not have start dates when they were created from the Template before I updated it, and despite updating them manually once the Project was created perhaps the Summary Task view was not picking them up somehow.  Not sure.  Will monitor, thanks

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...