Sam P Posted May 5 Share Posted May 5 Under New Project Risk, Weighting is a mandatory field however the default setting in Form Design sets it to be Read Only. It be easily changed but would suggest it should not be set to Read Only by default, thus removing the resulting error: Link to comment Share on other sites More sharing options...
Steve Giller Posted May 5 Share Posted May 5 The Project Risks wiki page states Quote The Risk Weighting will automatically be set based on the combination of the chosen impact and probability settings as defined in the Risk Matrix in the admin tool. Is it simply that you do not have any Weights defined? 1 Link to comment Share on other sites More sharing options...
AlexTumber Posted May 6 Share Posted May 6 @Sam P as @Steve Giller says, the weightings should be pulled through from the Risk Matrix which is defined in the administration section. You will need the Project Administrator role to access this: Alex Link to comment Share on other sites More sharing options...
Sam P Posted May 7 Author Share Posted May 7 Thank you @Steve Giller @AlexTumber yes I had missed this step, thanks for your help Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now