Ann Posted April 2, 2021 Share Posted April 2, 2021 Morning All Hope you are safe and well. Please would it be possible to advise if there is a way to clear the RAG Status of a task? Currently if the RAG Status is set to Red, Amber or Green there is no way of clearing the colouring? Thank you. Kind Regards Ann Link to comment Share on other sites More sharing options...
AlexTumber Posted April 6, 2021 Share Posted April 6, 2021 @Ann thanks for your post. I'll ask our development team to investigate. Alex Link to comment Share on other sites More sharing options...
AlexTumber Posted April 7, 2021 Share Posted April 7, 2021 @Ann this issue has been identified and fixed in the next Project Manager update. Alex Link to comment Share on other sites More sharing options...
Ann Posted April 12, 2021 Author Share Posted April 12, 2021 Afternoon @AlexTumber Hope you are well. That is fantastic, thank you. Do you know when the update will go live please? Thank you. Kind Regards Ann Link to comment Share on other sites More sharing options...
AlexTumber Posted April 12, 2021 Share Posted April 12, 2021 @Ann the next update was pushed live this morning. Your administrator can update now or it will update automatically this evening during your maintenance window. Alex Link to comment Share on other sites More sharing options...
Ann Posted April 12, 2021 Author Share Posted April 12, 2021 @AlexTumbercrikey that is quick. Fantastic news, thank you so much for your help with this. Hope you have a lovely evening. 1 Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now