Ann Posted February 12, 2021 Posted February 12, 2021 Afternoon All Hope you are safe and well on this chilly Friday afternoon. Another question, I have been asked by a project manager why when they add a new task the date is reverting to a date way in the past. I tried adding a task to a project and the due date did not change, however when you change the "Counts Towards Milestone" on the task the due date reverts to the due date of the milestone rather than today's date. Is this correct please? Thank you. Kind Regards Ann
AlexTumber Posted February 12, 2021 Posted February 12, 2021 @Ann thanks for your post. Yes that is correct behaviour. If a task counts towards a milestone then the due date is automatically set to be that of the milestone it is associated to. Alex
Ann Posted February 12, 2021 Author Posted February 12, 2021 Afternoon @AlexTumber, thank you that is fantastic. I will advise the project manager. Hope you have a lovely weekend.
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now