Will J Douglas Posted June 23, 2019 Posted June 23, 2019 Hi, I've created a new project, set a few milestones and added tasks to the milestones however the active tasks are now showing. Tasks are assigned to me, past the start date and before the due date but not showing in Active Is any one else having similar issues since upgrading? Regards, Will.
James Ainsworth Posted June 24, 2019 Posted June 24, 2019 Hi Will, I see that in your list of tasks you have one that it 100% complete and all the others have no progress. I'm curious, if you were to progress one of these tasks to have some percentage of progress, if they then show in the list of Active Tasks. I believe the idea behind that Active Tasks list is to show tasks that are currently being worked on. If there is zero progress, it may be considered as not active in this list. Regards, James 1
Will J Douglas Posted June 26, 2019 Author Posted June 26, 2019 Hi James, Yes you are right, my bad. I had assumed that the task would become active after the start date and time had passed rather than when progress was recorded. Thanks, Will. 1
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now