Lauren Posted February 14, 2019 Posted February 14, 2019 Hi We're trying to add a project resource to one of our projects. When clicking the button "Add a New Resource", nothing happens. Both the user listed as the "Project Manager" and I (we both have the highest permissions within Project Manager) are experiencing this. We've previously been able to add resources. Thanks Lauren
AlexTumber Posted February 14, 2019 Posted February 14, 2019 Hi @Lauren, thanks for your post. I'm sorry to hear you are experiencing problems. When you say add a resource, do you mean adding a new stakeholder? (small tabs on the right hand side of a project) Alex
Lauren Posted February 14, 2019 Author Posted February 14, 2019 Hi @AlexTumber No, we're trying to add resources to the "Resources" tab. We've added the required users as Stakeholders, but need them as resources to carry out certain functions within project tasks. Lauren
AlexTumber Posted February 14, 2019 Posted February 14, 2019 @Lauren resources are added automatically when you add project stakeholders (for every stakeholder you add, a resource record is automatically created). We plan on adding different types of resource in the future, not just 'People' and as this is the only type at the moment it makes no sense to have an 'add' button on the resources tab. I'm guessing the issue might be here that you have added the stakeholder and then deleted the resource record? Alex
Lauren Posted February 14, 2019 Author Posted February 14, 2019 Thanks @AlexTumber I've just tried adding a stakeholder and the number of available resources has increased Lauren 1
Lauren Posted February 15, 2019 Author Posted February 15, 2019 Sorry @AlexTumber - we've run into a couple of other issues surrounding project resources: 1) Deleting a stakeholder doesn't remove a resource - is this expected behaviour, given resources are added automatically when stakeholders are added? 2) Adding multiple stakeholders at once doesn't add multiple resources - as an example, I tried to add two stakeholders to a project. It added the two stakeholders fine, but only added the first stakeholder as a resource. Thanks Lauren
AlexTumber Posted February 15, 2019 Posted February 15, 2019 @Lauren no problem. When you delete a stakeholder, it does not automatically delete the resource. This is by design. It may be that you have recorded information against that resource (who then leaves the project as a stakeholder). By deleting the resource automatically this information would potentially be lost. As a stakeholder is added, it should automatically create a resource record. If this is not the case then I suspect we have a bug. I will pass this onto our development team to investigate. Alex
AlexTumber Posted February 15, 2019 Posted February 15, 2019 @Lauren our development team have identified and fixed this bug. The fix will be available in the next update. Alex
Lauren Posted February 15, 2019 Author Posted February 15, 2019 Thanks @AlexTumber Appreciate the quick turnaround 1
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now