Our trust is placing a "change Freeze" in place over the xmas week and we need a way to block out dates in the change calendar so none are scheduled.

From the 15th Dec to 1st Jan.

I have had a look at previous topics and the only thing I can find is:

However this was last year. and I am wondering if there has been any update? and if not if anything can be advised as a work around?

Hayley.

Link to comment
Share on other sites

Hi Hayley,

Thanks for your post.  We do have a change in our backlog for providing a change freeze period which originated from Nasim's post.  I've added you to the change.   Unfortunately this won't be available for you this week.

I will post back if I can come up with any ideas to work around this.

Regards,

James

 

Link to comment
Share on other sites

  • 11 months later...

A new feature has been made available which will allow you to block out days within the Change Calendar as Freeze Periods.

image.png

A user with the appropriate rights can add to the Freeze Periods.  Once a Freeze period has been set, this can be applied to BPM Operations that automatically raise changes, and to the Scheduling Action on a request where it will prevent users from scheduling during a Freeze Period.

For more information please see our documentation here.

Regards,

James

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...